Establishing cycling infrastructure in Almetyevsk
Team
Target audience
-
Жители и гости города
Practice description
Tasks:
Повышение комфортности городской среды за счет создания велодорожек и популяризации велодвижения.
Project’s major investor, Tatneft, contributed 250 million rubles in 2016, 200 million in 2017 and 2018, and 150 million in 2019 and 2020.
The project has 3 steps.
1. Establishing cycling infrastructure
The project was designed by Danish Copenhagenize Design Co.
- Guidelines for setting up the bikeways:
— The connectivity of a bicycle route must be ensured. Bike facilities should be established in the most significant places of the city.
— bikeways must be separated from motor traffic and from the sidewalk.
- Options for ensuring safety of cycle network:
— physical separation of bikeways by the existing green buffer;
— reduction of the roadways’ width;
— combination of the above mentioned options.
- The bikeways must comply with the international standards and have a width of 2.2 meters. In order to meet the quality standards, Almetyevsk MUE GUAD acquired a new paver, VÖGELE SUPER 800-3, with the pave widths ranging from 1.5 m to 3.5 m, and a new roller, Hamm HD 14, with the minimum spreading width of 1.5 m.
- High-quality cycling infrastructure should ensure:
— parking opportunities in yards, and on the premises of companies, as well as near educational and cultural institutions;
— bike repairs;
— intersection treatments;
— regulatory and warning signage, and markings;
— angled garbage bins along bikeways.
2. Making it accessible
- Winter maintenance of the bikeways is to be carried out with 4 brand new Hako Citymaster 1200 sweepers and 8 brand new MTZ-320 mini tractors. Anti-icing treatment involves using eco-friendly mineral salts, while the amount of salt to be used varies from 5 to 50 grams per square meter depending on the weather conditions.
- To improve accessibility, bike sharing service, Go Bike, is established. The rent is 10 rubles per 30 minutes.
- Comprehensive scheme of bike routes, parking opportunities and rental points is designed.
3. Promoting cycling
- A survey was conducted to study public opinions;
- Various cycling events are to be organized in order to promote bike using.
Practice result
Main result:
115,32 км. велосипедных дорожек построено за период 2016-2023гг.
Additional results:
за 15 мин. можно добраться из любой точки города до центра
на 14 000 т. в год снижено содержание СО₂ за счет увеличения числа велоперемещений, уменьшение числа автомобильных поездок
на 30% снизилась смертность населения за последние 3 года
Implementation cost: From 500 million to 1 billion ₽
Implementation features
Create analogue
Implementation stages
12 monthes
Подготовительный этап
The project is estimated to be implemented in 1 year.
The program involves creating 30 km of cycling facilities in the period of 2019-2020, it is expected to be fulfilled by 2021.